Building a new home is an exciting time but often we hear of stories of poor quality workmanship rearing its head once the final payment has been made to the builder and you’re settled in and just finished unpacking the last box of your things.
At IPI Norwest, we can help to provide you peace of mind that the quality of the work carried on your new home construction is of the highest quality and to the standard you would expect.
IPI Norwest can inspect your property at various stages of the construction. Whether you’re after a pre settlement completion inspection, or an inspection at each stage of the building process we are able to provide a package to suit your needs.
Most commonly customers request us to complete inspections in stages when the builder has asked for a progress payment. This is where we ensure the client is getting exactly what they have paid for.
Stage 1 - Piers Inspection
This is commonly know as site costs and is an added fee to your build. We can measure the piers to ensure the builder is not over charging you for these works.
Stage 2 - Slab Inspection
Once the slab is down we ensure the location and size is correct.
Stage 3 - Frames inspection
We ensure that the plans meet the actual build to ensure what you've paid for has been put into place.
Stage 4 – Pre Handover
At this stage we are inspecting the finished product including all floor coverings, paint work and fixtures and fittings.
Here, we really put your builder through their paces and closely scrutinise every detail of your new home to ensure any small defects and unfinished details are identified. Any defects will be ‘marked’ with a sticker so the builder is aware of the issue and will be recorded in your report.
Below are more detailed lists of the parts of the home inspected during this stage: External
Brickwork
Cleaning off of mortar from the face bricks
Chipped bricks and other imperfections in the mortar finish
Any other external cladding types such as weatherboards
Clearances between windows and brick sills are correct
Correct bearing of brick walls onto the concrete slab
Placement of articulation joints, flashings and weepholes is correct
The straightness and correct installation of guttering, fascia and eaves
Any damaged to pre finished paintwork of colour bond gutters, fascias and flashings
Roof
Scratches and chips on glazing
Internal
Doors are hung correctly and swing properly
Windows
Straightness of walls and skirting boards
Any tool marks, scratches or sanding ridges in the plaster joints
Ceilings for correct installation and any visible joints
Straightness of cornices
Finish of tiling and grouting
Tile junctions and joints
Seals around taps and splashback
All paintwork for coverage, blemishes and paint runs
Nail holes filled and covered correctly
Correct installation and no damage done to kitchen cupboards and bathroom vanities and bench tops
Correct installation of all plumbing fixtures and fittings
Stage 5 – Final Handover
Here your IPI Norwest Inspector will return to the property and ensure that any defects identified in Stage 3 have been suitably rectified and meet appropriate requirements.